Add an Estimate
Do one of the following:
Navigate to the Bid Board or Portfolio Planning tool and select the project.
Navigate to the project's Estimating tool.
Click the Estimating tab.
Click Add Estimate.
If you want to use an existing estimate, do one of the following:
Click Copy Selected Estimate.
If you want to create a completely new estimate, click Create Empty Estimate.
See the sections below for available options:
Adjust Estimate Settings
Click the vertical ellipsis
icon.The following modes are available for project estimates. Click a toggle ON
to activate the mode, or OFF
to deactivate it.Detailed Estimating
Group Multiplier
'Use' Tax Instead of 'Sales Tax'
Individual Labor Rates
Company-Wide Estimating Settings
Add Adjustments
Follow steps to Add Adjustments to an Estimate.
Add Inclusions and Exclusions
Follow steps to Add Inclusions and Exclusions to Estimates.
Create a New Group
In the section of the estimate that you want to add a new group to, click Create New Group.
Click into the title field to enter a new name.
Group By Requested Bid Item
Note: This feature is only available for bids sent with bid forms as part of the new Bid Management Enhanced Experience. If you have questions, contact the company that sent you a bid invitation.
Go to the group section in the Estimating tab.
Click Select next to 'Requested Bid Item'.
Choose the Requested Bid Scope Item to group by.
If you create a new group, you can drag the requested bid items to the new group.
Add Items
Tip
The following information is important when creating estimates:
On the right side of the row for a group, click the add
icon.Mark the checkboxes next to any items you want to include and click Select.
Enter information into each column as necessary: Note: The amounts that you enter for these fields will automatically calculate to populate the Total Cost, Sales Price, Total Sales, Profit, and Total Labor columns.
Budget Code:
Tip
If you have Procore Project Financials enabled, the budget code selections that are available have been imported from the project budget.
If you have the ERP Integrations tool enabled, budget code selections will be available from your connected ERP integration.