Assign a Budget Code in an Estimate in the Bid Board and Portfolio Planning Tools
Background
Within Procore, you can apply the same cost settings across all projects for consistency. However, projects can to differ from one project to the next. You can edit budget codes, which are made up of Cost Codes, Cost Types, Sub Jobs, and Custom Segments, to match your project's budget.
Example
For some projects you may hire a subcontractor and use the broader, standard cost codes for your company. For other projects, you may self-perform the work and have more granular tracking for the work in your budget.
You can set budget codes at every level of granularity for your estimate:
Individual Items
Assemblies
Groups
For each level of granularity, you can select to roll everything into a single budget code (the same sub job, cost code, cost type, custom segments) creating a single line item in your budget. Or, you can choose to use assign different budget codes to items, creating more granular line items in your budget.