Set Planned Amounts and Budget Line Items
Background
Setting planned amounts as lump sums, as high-level budget items, or simply syncing them with the Project level Budget tool allows capital planners to establish project budget constraints and plan projected costs into a multi-year capital plan.
Things to Consider
Required User Permissions:
'Standard' or 'Admin' level access to Capital Planning.
Additional Information
Program or project structures must be configured in Capital Planning.
Steps
Set Planned Amount as a Lump Sum
Navigate to the Capital Planning tool.
Click the name of the program or project you want to update.
Click Edit.
In the Planned Amount field, select Lump Sum as the type.
Enter the total dollar amount.
Click Save.
Set Planned Amount as Line Items
Navigate to the Capital Planning tool.
Click the Planned Amount for a specific project.
Select High Level Budget Items.
Add line items. For example, Hard Costs, Soft Costs.
Choose one of the following methods to enter values:
Enter a lump sum amount.
OREnter a quantity and unit cost to perform a unit-and-quantity calculation (quantity x unit cost).
Enter a %markup to perform a % calculation to add tax or contingency.
Click Save to update the total Planned Amount.
Sync Planned Amounts with Budgets
Navigate to the Capital Planning tab.
To sync the Planned Amount for an active project:
Select Project Budget in the Planned Amount Type column.
Select either the Original Budget or Revised Budget Option to sync with the Planned Amount.
Confirm the amount matches the current budget in the project-level Budget tool.
NoteThe budget data takes approximately 30 minutes to sync.
For Active Projects:
Select the option to sync with the Project Budget (Original or Revised Budget).
NoteChanges to the budget in the Procore® Budget tool will automatically update the Planned Amount in Capital Planning.