End a Resource Assignment
Background
Resource assignments allow you to manage your resources by assigning them to projects. You can end a resource assignment by updating the end date the current date.
Things to Consider
Steps
You can end resource assignments from the following places in Resource Planning:
Assignments List
Assignments List (Beta)
Assignments Boards
Assignments Gantt
Assignments Gantt (Beta)
End an Assignment from the Assignments List
Navigate to the Company level Resource Planning tool.
Click Assignments and select Assignments List.
Locate the desired assignment and click the gear
icon.Enter the new End Date.
Choose an option to save the assignment:
Click Save.
Select the caret
icon and select Save and Alert to save the assignment and send an assignment alert to the assignee.Optional: Update the 'Subject'.
Optional: Update the 'Alert Content'.
Select when to send the alert:
Send Now. Select this to send the alert immediately, then click Send.
Note: This will send the alert immediately based on the default or project assignment alert settings.Schedule. Move the toggle to the ON position to schedule the alert to be sent in the future.
Note: You can edit or send the scheduled alert at a later time.Select the Date and Time to send the alert.
Click Save.
Save Draft. Select this to save the alert as a draft. Then click Save.
End an Assignment from the Assignments List (Beta)
Beta
This feature is in beta and available for customers using the Resource Planning tool.
Navigate to the Company level Resource Planning tool.
Click Assignments and select Assignments List (Beta).
Select the assignments.
Hover over the assignment row and click the edit
icon.Mark the checkboxes for the assignments, then click the edit
icon.
Update the assignment information.
Click Update.
Send Assignment Alert Updates
After you create or update an assignment, send an alert to the assignee.