Considerações
Things to Consider
Only users with the Timesheets tool can access the 'Unit Quantity Based Budget' section in the project's Admin tool.
You don't need the Budget tool to import labor hours and production quantities. But if you have access to the budget tool, you should import a budget instead.
Procore recommends importing your budgeted hours only once. However, if you import a new version, the system will add new items and overwrite any changes to the original budgeted hours.
Supported Import File Type: XLSX
To ensure a successful upload, do not make any of the following changes to the file:
Rename any column headings.
Add, remove, or change the order of the columns.
Delete values in the Importer Data Fields tab.