View the Field Production Report

Steps

  • From the project's Reports tool

  • From the project's Timesheets tool

From the project's Reports tool

  1. Navigate to the project's 360 Reporting tool.

  2. Scroll to Project Reports.

  3. Click Field Production Report. See Which data columns are in a Field Production Report?
    FPR-accurate-12-13-18.jpg

  4. Click Add Filter and select one of the following filters to narrow the display results:

    • Cost Code

    • Sub Job Name

    • Unit Of Measure

From the project's Timesheets tool

  1. Navigate to the project's Timesheets tool.

  2. Click Reports.

  3. Click Field Production Report. See Which data columns are in a Field Production Report?
    FPR-accurate-12-13-18.jpg

  4. Click Add Filter and select one of the following filters to narrow the display results:

    • Cost Code

    • Sub Job Name

    • Unit Of Measure