Sync CI Changes

Background

Sync coordination issues to keep both Procore and Navisworks® up-to-date. The smoother workflow reduces errors and manual work. When both systems are updated, the responsible person is clear and accountable.

Things to Consider

  • Required User Permissions:

    • 'Admin' level permissions on the project's Coordination Issues tool.

Steps

  1. Click Sync CI Changes in Clash Manager.

  2. Review the changes.

  3. Select the coordination issues you want to sync.

  4. Click Sync Selected.