Create a T&M Ticket (Web)

Things to Consider

Beta

Company Administrators can enable the Resource Management: Rate Tables - Company & Project Rate Management beta in Procore Explore. (US 2 | UK)

Rate tables centralize and standardize your labor and equipment rates across all projects.

When you create rate tables, you define cost and billable rates for labor and equipment. You can also define which rates can be overridden at the project level.

Rate tables are then applied to projects and referenced by different Procore tools such as Timesheets and Equipment. They can be viewed in 360 Reporting, Analytics, and within some Procore tools.


Rates are configured in T&M Tickets and applied to Labor and Equipment entries. When a Change Event is created from a T&M Ticket, the revenue unit cost in each change event line item is pre-populated based on the rates from the T&M entries.

These cost rates are visible in the Change Event in the Change Events tool.

Note: To protect historical data from accidental changes, rates created in the table will be applied the next day.

Steps

  1. Navigate to the project's T&M Tickets tool.

  2. Click Create.

  3. Fill out the 'General Information' section of the form.

    Show/Hide Fields

    • Ordered By. The person in your project directory that ordered the work.

    • Location. The location the work was performed.

    • Reference Number. A reference number for the work.

    • Performed On. The date the work was performed.

    • Description of Work. A description of the work that was performed.

  4. In the 'Labor' section, enter labor information. Then click Add.

    Show/Hide Fields

    • Employee. The person in your project directory that performed the work.

    • Classification. The person's classification.

    • Time Type. The kind of time to be billed.

    • Hours. The quantity of hours worked.

  5. In the 'Materials' section, enter information for the installed materials. Then click Add.

    Show/Hide Fields

    • Material. The materials used to perform the work.

    • Description. A description of the materials.

    • Unit. The unit of measure for the materials.

    • Quantity. The quantity of materials used.

  6. In the 'Equipment' section, enter information for the equipment used. Then click Add.

    Show/Hide Fields

    • Equipment. The equipment in your project's equipment tool used to perform the work.

    • Description. A description of the equipment.

    • Quantity. The quantity of hours the equipment was used.

  7. In the 'Subcontractors' section, enter the relevant information. Then click Add.

    Show/Hide Fields

    • Company. The company listed in your project's directory.

    • Description. A description of the company.

  8. In the 'Approvals' section, select the Signees from the drop-down list.

    • Company Signee. A company signee is a person with signature authority for the company performing the work requested in the ticket.

    • Customer Signee. A customer signee is a person with signature authority for the entity that requested the labor, materials, or equipment being requested in the T&M ticket.

  9. Optional: In the Notes box, type any additional notes you want to add to the ticket.

  10. Optional: In the Attachments area, you can attach photos or any important documents, emails, or forms associated with the ticket.

  11. Click Save to create a T&M ticket is 'In Progress' and actively being worked on.