Spend on general conditions

This Project level Insights tool offers a broader perspective, allowing company to understand their general conditions spending trends across multiple projects.

  • Quick Insight: Provides a Company level benchmark such as: "Over the past 4 quarters, general conditions made up an average of 6.5% of each project's budget."

  • Percentage of budget allocated to general conditions for active projects: A line chart visualising the trend over the past 4 quarters and same time the prior year. Hovering over these displays detailed project and budget metrics for specific months.

  • Forecast availability: Indicates that predictive insights are available for a subset of projects.

  • Actions:

    • Go to report: Navigates to a Company level report or Dashboard related to general conditions spending.

    • Review Spend: Take you to a tear sheet listing projects with financial risk information.

  • Risk tags : Helps users quickly identify and prioritise high-risk areas within their projects. By categorising insights with High, Medium or Low risk levels, users can focus on the most critical issues at a glance.

  • How this insight is calculated: This insight calculates spend from the project’s direct costs and commitment payment applications and only includes costs recorded against the cost codes configured as general conditions. Each cost is assigned to a month using the following date fields:

    • Direct costs - Uses the Date field on the direct cost. If the Date field is blank, the insight uses the date the direct cost was created in Procore.

    • Commitment payment applications - Uses the Billing date field on the payment application. If the Billing date field is blank, the insight uses the Period end date. If both are blank, the insight uses the date the payment application was created in Procore.
      Note:: If your ERP integration has transaction syncing enabled, commitment payment applications are automatically synced to Procore as direct costs. To avoid counting the same cost twice, this insight only calculates spend from direct costs.

Project Spend General Conditions