Things to Consider
Only users with the Timesheets tool can access the 'Unit quantity based budget' section in the project's Admin tool.
You don't need the Budget tool to import labour hours and production quantity. But if you have the Budget tool enabled, you should import a budget instead.
Procore recommends importing your Budget hours only once. However, if you import a new version, the system will add new items and overwrite any changes to the original Budget hours.
Supported import file type: XLSX
To ensure a successful upload, do not make any of the following changes to the file:
Rename any column headings.
Add, remove or change the order of the columns.
Delete values in the importer data fields tab.