View the labour budget to actual report

Steps

  • View a report from the project's report tool

  • View a report from the project's timesheet tool

View a report from the project's report tool

  1. Navigate to the project's report tool.

  2. Scroll to the project report section.

  3. Click labour budget to actual to view the following information:

    • % Hours used. The percent of hours used that you have imported against the hours you have entered. This is calculated, actual hours ÷ Budget hours.

    • Budget Hours. The number of Budget Hours you imported.

    • Actual hours. The number of hours you have entered to date in Procore's labour tracking tools (Timesheets, My Time, Company Timecard and Site Diary).

    • Remaining hours. The number of hours you have remaining from the hours you imported against the hours you have entered. This is calculated, Budget hours - actual hours.

View a report from the project's timesheet tool

  1. Navigate to the project's timesheet tool.

  2. Click report.

  3. Click labour budget to actual to view the following information:

    • % Hours used. The percent of hours used that you have imported against the hours you have entered. This is calculated, actual hours ÷ Budget hours.

    • Budget Hours. The number of Budget Hours you imported.

    • Actual hours. The number of hours you have entered to date in Procore's labour tracking tools (Timesheets, My Time, Company Timecard and Site Diary).

    • Remaining hours. The number of hours you have remaining from the hours you imported against the hours you have entered. This is calculated, Budget hours - actual hours.