Determine the order in which variations were approved
Background
If you need to delete a variation after it is placed in the 'Approved' status, you must remove the 'Approved' status from all 'Approved' variations that have been approved since that particular variation. To do this, find the most recently approved variation. Then, update each variation's status to 'draft' working backward until you locate the variation that you want to edit.
If you approved variations in this order: 001, 002, 003
You must remove the 'Approved' status from variations in reverse order: 003, 002, 001.