Locate the commitment contract to work with. Then click its Number link.
Click the Variations tab.
Click Create potential VAR.
Complete the following fields:
Sign with DocuSign® Mark this tickbox to route the potential variation for signature via the Procore + DocuSign® integration. This allows you to collect signatures directly from Procore without exporting the document.
How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log in to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.
Number Accept the default number, enter a new number or create a custom numbering scheme.
Revision Shows the revision number. The first version is zero (0), subsequent revisions are assigned in sequential order. A PV might have several revisions, depending on its reviewer/approver feedback.
Date created Shows the creation date and time. This value cannot be changed.
Contract If you have been assigned access permission to the commitment tool, click this link to open the contract.
Reference Add any other important tools, materials, drawings or documents to use as a reference for the PV.
Contract company Shows the name of the company responsible for performing the work on the contract.
Private Mark this tickbox if you only want the PV to be visible to users with 'Admin' permissions on the Commitments tool.
Created by Shows the Procore user who created the PV. This value cannot be changed.
Executed Mark this tickbox to set the PV status to Executed and apply its financial values to your Budget and commitment logs.
Signed variation received date Select the date when the fully signed variation document was received back from all signing parties.
Designated reviewer Select the Procore user assigned to review, evaluate and process the PV.
Change reason Select the reason for the PV, either client request, design development, allowance, existing condition, back charge or any additional options created for your specific environment by your company's Procore administrator. See Set the default change management configurations.
Programme impact If known, provide an estimate for the additional number of days required to complete work when the PV is approved.
In Beta
Note to users participating in the 'Subcontractor Estimated Completion' limited release beta programme. When a user places a variation in the 'Approved' status and it includes a value in 'programme impact' field of the variation, Procore automatically updates the 'estimated completion date' field in the commitment contract by the number of days entered.
Field change Tick this box if the PV requires a field change.
Paid in full Tick this box to indicate you have received payment for this change.
Paid date Select or view the date when the payment for the item was actually issued or completed.
Amount Enter the total value associated with the line item, variation or payment application.
Request received from Select the Procore user for whom you are submitting the PV.
Description Enter a more detailed description of the reason for the PV.
All cost codes related to the sub jobs will appear in the following field.
For contracts using the amount based accounting method:
Change event line item If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.
Description Enter a description for the line item. For example, type: Monthly service fee
Amount Enter the amount of the cost.
Billed to date The system automatically calculates the amount billed on the commitment up to the current date.
Amount remaining Enter the amount that has NOT been billed to the current date.
Tax code Enter a tax code to use for this line item. This field only appears if you have enabled the tax code feature. See How can I use tax codes on a project?
For contracts using the unit quantity based accounting method:
Change event line item If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.
Unit cost Enter the unit cost in the box provided.
Amount The system automatically calculates the subtotal for you, based on the quantity, UoM and unit cost entry.
Click Save. A GREEN banner appears to indicate that the bill of quantities is saved.
Important
If you assigned a budget code that is not currently represented on your budget or if leave the budget code field blank, a confirmation message appears. To proceed, you must click OK to acknowledge the message. This action adds the corresponding line item(s) to your project's budget as non-budgeted line items.