Manage valuation periods
Procore can be configured to use terminology specific to main contractors, owners or specialty contractors. Learn how to apply the dictionary options.
What do you want to do?
A valuation period defines the billing cycle used by a project’s team and payment application contacts on Procore’s payment applications and progress billings. In addition to defining the frequency of the billing cycle (for example, monthly or weekly), a valuation period also defines the billing cycle’s start/end date and the due date for the payment application or progress billing.
For payment application administrator
Only payment application administrators can create or edit valuation periods. When billing cycles have consistent start, end and due dates, create automatic periods. To support flexible billing cycles, create manual periods. Whichever option you choose, you can only have one (1) valuation period in the Open status at a time when managing payment applications.