Create automatic valuation periods

Using owner or specialty contractor terminology?

Procore can be configured to use terminology specific to main contractors, owners or specialty contractors. Learn how to apply the dictionary options.

  • To learn the differences: Show/Hide

    • This table shows the differences in tool names (bold) and terms across the point-of-view dictionaries for Project Financials.

      Main Contractors
      English (United States) - Default

      Owners
      English (Owner Terminology V2)

      Speciality Contractors
      English (Speciality Contractor Terminology)

      Payment applications

      Payment applications

      Progress Billings

      Owner

      Funding

      Owner

      Owner/Client

      Owner/Client

      MC/Client

      Main Contract Variation

      Funding Variation

      Client Contract Variation

      Main Contracts

      Funding

      Client Contracts

      Revenue

      Funding

      Revenue

      Subcontract

      Contract

      Subcontract

      Subcontractor

      Contractor

      Subcontractor

      Subcontractor Bill of Quantities (SBOQ)

      Contractor Bill of Quantities (CBOQ)

      Subcontractor Bill of Quantities (SBOQ)

      About these dictionaries
      • Default setting: The 'main contractor' dictionary is enabled by default for all accounts.

      • Availability: These alternate dictionaries in italics are available in US English only.

      How to switch your dictionary

      To change your company's terminology to the owner or specialty contractor dictionary, contact your company's . They will work with your Procore point of contact to make the change.

Background

A valuation period defines the billing cycle used by a project’s team and payment application contacts on Procore’s payment applications and progress billings. In addition to defining the frequency of the billing cycle (for example, monthly or weekly), a valuation period also defines the billing cycle’s start/end date and the due date for the payment application or progress billing.

Examples

Common valuation periods include:

  • Monthly
    Examples of common monthly valuation periods are below:

    • Starts on the 1st day of a month and ends on the 30th of the same month.

    • Starts on the 15th of one month and ends on the 14th of the following month.

  • Weekly
    Examples of common weekly valuation periods are below:

    • Starts on Sunday of this week and ends on Saturday of this week.

Things to Consider

  • Required User Permissions

  • Additional Information:

    • When you create a new valuation period Procore automatically sets:

      • The new valuation period's status to Open.

      • The previous valuation period's status to Closed.

      • There can only be one (1) valuation period in the Open status at any given time.

    • You can only create valuation periods in the Project level Payment Applications tool.

      • You cannot create or manage valuation periods at the Company level.

    • These payment application management features rely on valuation periods:

Prerequisites

Steps

  1. Navigate to the project's Payment Applications tool.

  2. Optional: Click the valuation period tab.

  3. Click the Create valuation period button.
    Start New Billing Period

  4. In the 'Set up valuation period' dialog box, click Automatic.

  5. Under 'Automatic', configure the valuation period's setting as follows:
    Set Up Automatic Billing Period

    • Frequency

      • Monthly. Select this option then choose the date you want the valuation period to start.

      • Weekly. Select this option then choose the date you want the valuation period to start.

      • Never. Select this option to never create an automatic valuation period.

         Tip

        When would I choose the 'Never' option? If you have previously configured Procore to automatically create new valuation periods, you can cancel that process at a later time by clicking Create valuation period and selecting the 'Never' option in the Automatic tab as described above. This overrides the tool's previous valuation period creation settings and stops Procore from creating new ones.

    • Start date. Select the date of each month you want the valuation period to start.

       Note
      • To create automatic valuation periods that occur after your selected 'start date', you must manually create the first valuation period on your project with the Payment Applications tool. See Create manual valuation periods.

      • Keep in mind that Procore creates automatic valuation periods for future periods on the future period's start date. For example, if you want to automatically create valuation periods that start on the first of the month, Procore automatically creates the new valuation period on the first of each month.

    • End date. Select the date of each month you want the valuation period to end.

    • Due date. Select the date of each month you want the payment application to be due.

  6. Click Save.

Next Steps

See Also

Loading related articles...