Create a receipt
Background
You can use Procore to manage materials for your project. From the Materials tool, you can create receipts to track the materials you have received and any defects. You can create receipts for orders placed outside of Procore or approved commitment change or purchase order made in Procore's commitment tool.
Things to Consider
If you selected an associated purchase order, line items are filtered to the change or purchase order.
If you selected an associated shipment, you can only add the items in the shipment, not the entire change or purchase order.
You can only manually create material items if there is no purchase order or shipment associated with the receipt.
When splitting line item, the item quantity will always equal the total quantity received.
Defect creation
Defects are automatically created when a receipt is finalised.
If the quantity received is less than the the quantity expected, a Short defect is created.
If the quantity received is more than the quantity expected, an Overage defect is created.
If the condition for items marked as Damaged or Unacceptable a defect is created.
Prerequisites
Locations must already be created in Procore. See Add locations to a project.
Materials must be listed in your inventory using one of the following methods:
On an active project, the commitment tool was used to create a commitment variation or purchase order for materials and includes the following information:
The status is Approved
The Bill of Quantities (BOQ) includes the following for each line item:
Description
Unit of Measure (UoM)
Steps
Navigate to the project's Materials tool.
Click Create and select Receipt.
Enter the Date Received.
Save or submit the receipt.
Click Save as Draft to save the receipt as a draft.
Click Submit to submit the receipt for approval.