In Procore, a purchase order (PO) is a formal financial commitment documenting the specific types, quantities and agreed-upon prices for products or services. These orders are an essential part of the procurement process. A buyer (for example, a main contractor) creates and issues a PO to a seller (for example, a subcontractor) to cover the cost of a contract. Once the seller has accepted the PO, it represents an agreement between both parties.
and
A subcontract is a legal agreement where a party on a main contract engages a third party (the subcontractor) to perform all or part of the work defined in the main contract.
are called commitments. A commitment is a contractual agreement between a buyer (for example, a project owner, a main contractor or a specialty contractor) and a seller (for example, a contractor, a subcontractor or a vendor). The seller is responsible for completing project work or fulfilling an order for the buyer. When you need to alter the terms of the original agreement, you can create a commitment variation.
Important
When the change event tool is enabled on a project
The process that you will use to create a commitment variation in Procore depends upon a few factors. First, if the change event tool is disabled on the project, you will use one of the processes below. Also, keep in mind that the number of steps required to create a commitment variation is dependent upon the variation tier setting that is configured on the project's commitment tool. See Configure the number of commitment variation tiers:
1-tier configuration:
Create a commitment variation as described below.
2-tier configuration
Create a commitment potential variation
Create a commitment variation
Things to Consider
Required User Permissions:
'admin' level permissions on the project's commitment tool
'Standard' level permissions on the project's Commitments tool and added to the 'Private' drop-down list and the 'Allow standard level users to create CVs' configuration must be selected.
Additional Information:
If the change event tool is disabled on the project:
If your company is using the ERP Integrations tool: Show/Hide
Additional requirements, considerations and limitations vary depending on the ERP system your company's account is integrated with. Most ERP systems have limitations on the number of characters that can be used for a commitment's title. See Things to know about your ERP integration for details.
Sign with DocuSign® If you have enabled the Procore + DocuSign® integration (see Enable or disable the DocuSign® integration on a Procore project), a tick appears in this box by default. If you do NOT want to collect signatures with DocuSign®, remove the mark.
Tip
How do you collect signatures with DocuSign? After the data entry for the item is complete, Procore recommends changing the item's status to 'Out for Signature' before clicking the Complete with DocuSign button to launch the DocuSign® application. If you have not previously signed in, you will be prompted to Log in to DocuSign®. Once you are signed in, you can prepare the DocuSign_®_ envelope for signatures. After the signature process is complete, Procore automatically changes the status of the item to 'Approved' and marks the item as 'Executed'. To learn more, see DocuSign®.
Number This field automatically populates based on the number of variations already created. By default, the number will automatically increment by one.
Displays the variation's revision number. When a variation is first created, its revision number is zero. A variation could have multiple revisions because of feedback from a reviewer/approver.
Date created Automatically populates with the date that you create the commitment variation. The date cannot be changed.
Created by Automatically populates with the name of the user who is creating the variation.
Contract company Automatically populates with the name of the subcontractor or vendor listed on the subcontract. This field is only available for subcontracts.
Contract Automatically populates with the name of the contract for which the variation is being created. This field is only available for subcontracts.
Title Enter a name for the variation. The maximum character limit is 255 characters.
Private Mark this tickbox to make the variation visible only to users with 'admin' level permissions on the Commitments tool.
Change reason Select one of these reasons for the potential variation: client request, design development, allowance, existing condition or Contra charge. To learn how to configure change reasons, see Set default change management configurations.
Accounting method This field inherits the accounting method that was specified in the contract.
Due date Select a due date for when the variation must be approved by.
Payment application date Select the date when the variation was payment application.
Designated reviewer Select the Procore project user at your organisation who will be responsible for approving or rejecting this variation later. See Approve or reject commitment variations.
Important
The 'designated reviewer' can submit an approve or reject response only when a variation is in the Pending - In Review status.
To send an email notification to the 'designated reviewer' to notify that person that a variation is awaiting their response, you have these options:
The pending variation will also be listed in the 'My open items' area in the project's Home page. The user can check this page at any time.
After the 'designated reviewer' submits an approve or reject response, the 'Reviewer' field (directly below the 'designated reviewer' field) shows the date/time stamp of that user response. The 'Reviewer' field is only visible to the 'designated reviewer.'
Request received from Select a user from the project's Directory who you are submitting the variation on the behalf of.
Description Enter a detailed description of the variation.
Notes
If you are exporting the variation to Sage 300 CRE® and Integration by Procore, entry exceeding one thousand (1000) characters will be truncated during the export.
If you will be exporting the variation to a different integrated ERP system, you can to enter an unlimited number of characters in Procore.
Programme impact If known, you can provide an estimate of the number of additional days that would potentially be added to the current Project Programme if the variation were approved.
In Beta
Note to users participating in the 'Subcontractor Estimated Completion' limited release beta programme. When a user places a variation in the 'Approved' status and it includes a value in 'programme impact' field of the variation, Procore automatically updates the 'estimated completion date' field in the commitment contract by the number of days entered.
Location Use the location drop-down menu to select a location the [item] impact. Either select from the predefined locations or add a multi-tiered location. See Add a multi-tiered location to an item. This location may be as general as the site location at the first tier or as specific as where on the site the contractor will be working at the second tier.
Reference Reference any other tools, materials or documents that are related to the variation.
Executed Mark this tickbox if the variation has already been executed.
Field change Mark this tickbox if the variation requires a field change.
Paid in full Mark this tickbox if the cost is already covered in the Budget.
Attachments Select and add any relevant documents.
Click Create or Create & email to send the variation to any users listed as 'Reviewers'.
Add a bill of quantities (BOQ) to the variation
If there are cost associated with the variation, add line item to the variation's bill of quantities (BOQ).
Click the Bill of quantities tab.
Click Edit.
Click Add line.
Main contract line item Select a line item from the drop-down list. If there is no line item that fits, select Not Budget.
Change event line item Select a change event line item from the drop-down list.
Description Type a description for the new variation.
Cost amount Enter an amount in the box.
Optional:Tax codes If you are using tax codes with this project, select a tax code to use for the line item.
Tip
Don't see the tax code field? This field only appears when the tax code feature is enabled on the Procore project. See How can I use tax codes on a project?
Click Add
Repeat these steps for each line item.
Click Save.
Note
For companies that have enabled the ERP Integrations tool
After the commitment variation is placed into the 'Approved' status in the Commitment tool, project managers will typically send the variation to the ERP Integration tool where it must be accepted by an accounting approver for export to the integrated ERP system. For instructions, see Send a CV to ERP Integration for accounting acceptance.