Respond to an RFI
Background
If you are listed as an 'assignee' of an RFI, it means that your response has been requested. It's strongly recommended that you enter a response as soon as possible to ensure that the RFI can be resolved in a timely manner. Remember, an RFI may require the response from multiple persons before it can be sufficiently resolved. The RFI will remain assigned to you, which means you're listed as the Ball in Court person until you submit a response. To view a common workflow of the RFI process, view the workflow diagram.
Things to Consider
Additional Information:
For enhanced security, attachment links within RFI notification email are designed to automatically expire 90 days after the email is sent.
If you click an attachment link that is older than 90 days, you will be automatically routed to the Procore login screen. Simply enter your Procore credentials to sign in. As long as your account has access to the project, the link will automatically renew and the file will immediately download. There is no limit to how many times an authorised user can renew an expired link
Steps
When you are designated as the 'assignee' on an RFI, you have different options for submitting a reply. Each option logs your reply in the appropriate project's RFI tool:
After you submit your response to the RFI, the system automatically shifts the Ball in Court responsibility to the RFI manager. Email notifications and in-app notification centre cards are generated according to the project's existing notification settings.
Next Steps
The next steps are typically completed by an RFI manager (see What is the RFI manager role?) or a user with 'admin' level permission to the RFIs tool:
If you want to obtain more information from another user, follow the steps in Edit an RFI and designate the other user as the assignee on the RFI.
If the RFI received only one (1) reply and that response satisfies the information requirements, follow the steps in Close an RFI.
If the RFI received multiple replies, you can review the replies and designate the one that satisfies all the information requirements as the 'official response'. See Choose an "official response" for an RFI.
See Also