Enable Dynamic Submittal Plan

Important

To avoid unintentional re-calculations, the 'Enable Dynamic Submittal Plan' setting is disabled by default for any project that already contains submittals with a workflow applied. Please reach out to your Procore point of contact for assistance with enabling this feature.

Steps

  1. Join the Dynamic Submittal Plan open beta in Procore Explore.

  2. Enable the Dynamic Submittal Plan in the project level Submittals tool.

    • Click the Configure Settings Icon Settings Gear Grey3icon.

    • Under General Settings, go to the Schedule Linking section.

    • Select Enable Dynamic Submittal Plan.

  3. Set a default Buffer Time and Prepare Time for the project.

  4. If you do not use collaborative submittal workflows, set a default Internal Review Time and Design Team Review Time.

Important

If you enable the Dynamic Submittal Plan on an in-progress project, a migration process runs for your existing items. If any items fail to migrate, click the failed count link in the migration toast message to review and resolve the errors directly.