Reset a Project Schedule
Background
Redefine a project's scheduling path by transitioning from an imported file to a schedule built entirely within Procore. The reset function allows you to wipe current data and restart the configuration process. Only perform this action when you require a total reset of the project timeline.
Things to Consider
'Admin' level permissions on the project's Scheduling tool.
This action deletes all existing tasks, look-ahead details, and dependencies.
Data cannot be recovered after you confirm the reset.
Steps
Navigate to the project's Scheduling tool.
Click the Settings
icon.Select Project Schedule from the drop-down menu.
Click Reset to Original Empty within the Schedule Information section.
Note: If you do not see this button, verify that you have 'Admin' level permissions.
Review the warning regarding data loss in the confirmation window.
Click OK to reset the tool.
Note: You will be redirected to the initial 'Add a Schedule to Procore' screen.