Fix Dynamic Submittal Plan Migration Errors

When enabling the Dynamic Submittal Plan on an in-progress project, some existing submittals may fail to migrate due to schedule or workflow conflicts. This task allows you to easily identify failed submittals, view specific failure reasons, and resolve the errors directly so the migration can complete without contacting Support.

Things to Consider

  • Recycle bin submittals are completely excluded from the migration. If you want a deleted submittal to migrate, you must restore it before initiating the migration.

  • The error banner automatically disappears once the submittal is successfully fixed.

  • Preparation: The Dynamic Submittal Plan migration must already be initiated on an in-progress project.

Steps

  1. Navigate to the project's Submittals tool.

  2. Click the failed count link within the migration toast message. This filters your list to display only the failed items.

  3. Select a failed submittal to open its details page.

  4. Review the human-readable failure reason displayed in the error banner at the top of the page.

  5. Use the DSP Migration Errors table below to determine your exact fix, and update the submittal's workflow or dates accordingly.

  6. Click Save to finish migrating the submittal.

DSP Migration Errors

Migration Error

How to Fix

A workflow step already has a response, but the next step's due date is on or before that response date.

The workflow has already started. In the workflow table, set the next step's due date after the previous response date (returned date).

The Final Due Date is on a non-working day and the Required On-Site Date is blank, so a new date can't be calculated.

Either set the Required On-Site Date, or move the Final Due Date to a working day (Monday–Friday)

A later workflow step is due on or before an earlier one, so days to respond can't be calculated.

The workflow has not started. In the workflow table, set each step's due date in chronological order so that each step's due date is after the step before it.

The Submit By date is outside the supported range.

Change the Submit By date to a year between 2000 and 2125.

The Final Due Date needs to match the Required On-Site Date minus lead time.

Change the Required On-Site Date or the lead time so the Final Due Date satisfies the rule.

Something went wrong on our end. Contact support to finish migrating this submittal.

Contact Procore Support to finish migrating the submittal.