Edit the Advanced Settings Tab on a Commitment
Background
When working with an individual commitment contract, a user with 'Admin' permission on the project's Commitments tool has the ability to use some advanced settings that apply only to that commitment. For best results, it is recommended that you configure the advanced settings before you add line items and before you create your downstream commitment invoices.
Things to Consider
Required User Permissions:
'Admin' level permissions on the project's Commitments tool.
Additional Information:
For best results, configure the advanced settings before you add line items to the SOV and before you create invoices against the commitment contract.
Additional settings can be configured by an administrator. See Configure Advanced Settings: Commitments.
Prerequisites
Create a Commitment
Steps
Navigate to the project's Commitments tool.
Under the Contracts tab, locate the purchase order or subcontract. Then click View.
Click Advanced Settings.
Click Edit.
Under Edit Advanced Settings, turn features ON and OFF as follows:
Comments* Enable Comments. Place a checkmark in this box to provide users with 'Admin' level permissions on the project's Commitments tool with the ability to add comments.
Financial Markup* Enable Financial Markups. Place a checkmark in this box to provide users with the ability to add financial markup to change orders. To learn more, see Add Financial Markup to Commitment Change Orders.
Payment* Enable Payments: Place a checkmark in this box to enable the 'Payments Issued' tab on the commitment contract. This gives you the ability to add new payments to the commitment. To learn more, see Add a New Payment to the Payments Issued Tab of a Commitment.
Invoice* Enable Completed Work Retainage. Mark this checkbox to enable a data entry field that gives users the ability to specify completed work retainage on the commitment contract. Remove the mark from this checkbox to change the 'Default Retainage Percent' setting on the commitment to zero (0) percent.
Important
For best results, it is recommended that you decide whether you want to turn the 'Enable Completed Work Retainage' setting ON or OFF before you begin creating subcontractor invoices for the commitment contract.
Schedule of Values* Accounting Method. Choose the accounting method that you want Procore to use on the commitment. Your choices are Amount Based or Unit/Quantity Based.
Important
It is important to verify that the accounting method that you want to use is set when you first create a commitment and before you add line items to the Schedule of Values (SOV). You cannot change the accounting method after creating a line item. To learn about the things to consider, see How do I set the accounting method for a contract or funding?