Fill a Resource Request Using Smart Bench
Background
Resource requests are an efficient way to let your team know that you need a resource for a particular project. Create a resource request when you need a resource but aren't sure who to assign, or if you do not have permissions to create assignments yourself.
After a request is created, a resource can be assigned to fill that request. Use the Smart Bench to fill requests based on a resource's tags, availability, distance, and job title match the request.
Things to Consider
The order of the resources on the Smart Bench is determined by how well the resource's tags, availability, distance, and job title match the request.
On the Gantt, you can use the Smart Bench to fill any labor request.
On the Boards, you can use the Smart Bench fill labor requests that start the following day and going forward.
Smart Bench currently supports labor requests.
By default, the Assignment Boards will show all outstanding requests, regardless of the date selected. To only show requests for the day you are viewing update the defaults when viewing the Assignment Boards. See View the Assignments Boards.
Prerequisites
Steps
Project Details
Fill a Resource Request from the Assignment Boards
Navigate to the Company level Resource Planning tool.
Click Assignments and select Boards.
Locate a request with the that begins in the future and has the smart bench
icon.Click the request to see resources that most closely match the request.
Optional: Click Reset to see all resources.
From the 'Bench', drag and drop the resource on to the request to assign the resource.
To send an assignment alert, edit the assignment and click Update and Alert.