Change management tools
Next, start learning about Procore's change management tools. You can create two types of variations in Procore. There are two options for setting up these tools: (1) variations with change events or, (2) variations without change events.
Variations with change events
Creating a change event allows you to prepare for the impact of the change before it becomes an actual cost - which is an important part of a speciality contractor's contract management strategy when hiring outside subcontractors to perform task.
After creating a change event, you can then create an RFQ (request for quote), which is sent to the appropriate subcontractors for pricing. When RFQs are created and responded to by the assigned subcontractors, variations can then be created based upon the submitted quote.
Configure your variation tier setting. You can choose between a one (1)-, two (2)- and three (3)-tier variation setting. Each tier adds a layer to your team's overall change management workflow. A lower number of tiers offers the most straightforward workflow. An increased number of tiers provides your team with a more complex workflow but gives your team more control over changes. The most common settings among Procore users are to use the one (1) or two (2) tier setting.
ExampleA common example of a client contract (2) tier use case is when you want to mimic your main contractor's bundling of variations in your Procore account. If you tend to issue variations immediately and bill for them on a one-by-one basis (regardless of the approval bundle), a (1) tier variation setting might be the better choice. To learn more, see What are the different variation tiers?
Create change events. On a construction project, a change event is any change that affects (or potentially affects), the original scope of a construction project. There are numerous ways to create change events in Procore. In addition to using the change events tool (see Create a change event), you can also use any of the options available in supported Procore tools or using Procore's mobile platform. For details on those options, see Which Procore tools can I use to create a change event?
Create RFQs from change events and review RFQ responses. If you need to create an RFQ for your subcontractors to submit pricing, see Create RFQs from a change event. You can then review your subcontractor's quotes to determine if you want to move ahead with creating a variation. See Review RFQ responses.
Create variations. You can create two types of variations in Procore:
A commitment variation can be created before or after an RFQ response is submitted. See Create a CV from a change event.
A potential variation can be created before or after an RFQ response is submitted. See Create a PV from a change event.
To learn what else you can do with the change event tool, see change event.
Variations without change events
When the change events tool is disabled, your team will create changes using the commitments and client contracts tools. Most variations start with a potential variation which would be generated in the client contracts tool. Below is a description of the process when all three (3) tiers are enabled for client contract variations.
Create a potential variation. Create a potential variation to outline any potential change in cost that would affect the contract. When you fill in a Bill of Quantities (BOQ) for a potential variation, you'll have the option to select a budget code and enter the pound amount. Ideally, it will be a budget code already in the Budget, so you can see the Budget increase on the Budget tab.
Create a commitment variation. After creating a potential variation, you can create a commitment variation that acts as a request for pricing from the subcontractor who will be responsible for the scope of work outlined in the potential variation. You can compare the commitment variation to the corresponding potential variation and view your variance between the two.
Create a variation request. After you've created potential variations, you can roll them into variation requests. Variation requests are typically the documents that are submitted for approval and can be used for submitting either individual potential variations or for grouping potential variations in order to streamline the review and approval process.
Create a client contract variation. Variations with a status set to 'Pending' will appear in the 'Pending budget changes' column of the project's Budget tool. Approved CCCOs can be added to main contract payment applications. Once you have marked the client contract variation as approved, the total pound amount change will be reflected in the 'Approved COs' column on the Budget tool.
Create a commitment variation. A commitment variation outlines variations in cost that affect the contract between the contracting company and a vendor or subcontractor. Once you have marked the commitment variation as approved, the pound change will be reflected in the 'committed costs' column on the Budget tool. Commitments and potential commitment variations with a status of 'Pending' will show up in the 'pending cost changes' column on the Budget tool. See Create a commitment variation.
To learn what else you can do with the variation tool, see variation.