View a main contract's variations (Beta)

Background

To navigate to the variations associated with a main contract, click the Variations tab in the contract. The number of sections in this tab corresponds to the number of variation tiers configured for the project's Main Contracts tool. See What are the different variation tier settings in Project Financials?

Available sections in the variations tab

This table shows which variation sections are available in the variations tab of a main contract.

Variation tier

Main contract variations MCVs

Variation requests VRs

Potential variations prime PVs

One (1) tier

Icon Mindtouch Table Check

Icon Delete X

Icon Delete X

Two (2) tiers

Icon Mindtouch Table Check

Icon Delete X

Icon Mindtouch Table Check

Three (3) tiers

Icon Mindtouch Table Check

Icon Mindtouch Table Check

Icon Mindtouch Table Check

These are the available columns in each section's table

Number, revision, title, status, amount, date initiated, due date, review date, designated reviewer, PVs

Number, revision, title, status, amount, date initiated, due date review date, designated reviewer, PVs

Number, revision, title, status, amount, programme impact, date initiated, change reason, VR, MCV, change events, change event type

Things to Consider

  • Required User Permissions:

    • Private contracts:

      • Admin level permission on the main contract tool.
        OR

      • Standard level permissions on the main contract tool can see variations they have created.

  • Additional Information:

    • The number of sections in this tab depends on the number of variation tiers configured in the main contract tool.

Prerequisites

Depending on the number of variation tiers configured in your environment, you will need to create one (1) or more of the following item for your main contract, in order for Procore to list in the available section.

Steps

  1. Navigate to the project's main contract tool.

  2. In the contracts table, locate the main contract.

  3. Click the contract's Number link to open it.

  4. In the contract, click the variations tab.

    Example

    Depending on the number of variation tiers configured in your environment, the 'Variations' tab includes one (1) to three (3) different sections. See Configure the number of main contract variation tiers.

    Prime Contract Change Orders Tab

  5. Choose from these options:

    • To open a variation, click one of the hyperlink in the table in the variation section.

    • To export a list of the variations, click the PDF or CSV button at the top of the table.