Overview
Billing for stored materials on a construction project allows contractors to recover the cost of purchasing and storing materials on a job site. It also requires teams to ensure they accurately account for materials received. This includes documenting the trade partner, types of materials, quantity, cost and delivery dates. Because stored materials do not represent completed work, payment applications must be itemised to differentiate between what is installed on a project during a valuation period and what is stored for future work.
Once a contractor receives a payment application payment, stored materials become the client's property and the contractor is responsible for ensuring stored materials are safe. To avoid misunderstandings, ensure the requirements in a project's commitment or main contract are clear about how to bill for stored materials.
Teams using the Procore payment application management solution can manage stored materials manually or enable a configuration option that moves balances from the 'Materials Presently Stored' column on a previous payment application to the 'Work Completed from Previous application' column on the next payment application. Users also bill for stored materials using the accounting method configured for the contract.
In addition, teams can configure a Procore project template, so the stored materials configuration setting are automatically copied to new Procore projects. To learn more, see What gets copied over to a new project when applying a project template?