Considerations
Prerequisites
To bill for stored materials, your team must:
Track the materials you receive and document them in your inventory.
Track the materials installed during a valuation period and those stored for the future.
TipNeed help tracking materials? For tip about using different Procore tools to track materials received and installed, see How do I track the actual materials received and installed on a job site?
You also need to:
Step | On main contract payment applications... | On subcontractor payment applications... |
|---|---|---|
Opt into the modernised payment application experience | ||
Create a contract | ||
Create a payment application |
1 In Procore, a commitment is either a purchase order or a subcontract.
When your team creates owner or subcontractor payment applications, you bill for line items as other project costs. The only difference is that the materials installed and the materials stored are documented on the payment application.