Amount-based data entry
Review this example to learn how to bill for stored materials on payment applications when a contract is configured to use the 'Amount-Based' accounting method.
For the contract's first payment application, the value in the New materials stored column is always set to £0.00 by default. Since the subcontractor received materials on-site during this valuation period, the payment application contact enters £2,000.00 in the New materials stored column (see 1). This represents the currency amount of the materials received. Once input, Procore automatically update these values on the line item (see 2):
Total completed & stored to date (%). Procore converts the entry to a percentage value (16%) to show total progress.
Materials presently stored. Procore update this column with the amount in the New materials stored column (£2,000.00).
Total completed & stored date (£). Procore adds the £2,000.00 entry to this column (see 2). Note: This column shows the cumulative total of the values in the Work completed this period, New materials stored and Materials presently stored column.
Balance to finish. This column is only visible to payment application administrator(s). Procore takes the scheduled value amount and subtracts the new materials stored amount to calculate the balance to finish). Note: In subsequent payment applications, this column shows the cumulative decline from the contracted amount for the line item.

For the next valuation period, the payment application contact prepares their second payment application. In all new payment applications, the New materials stored column is always set to £0.00 by default (see 1). However, Procore automatically moves the value from the New materials stored column on the previous payment application to the Previous materials stored column on the current payment application (see 1 to 2). Before making additional data entry, note that the highlighted values (see 3) match the first payment application (above).

Next, perform some additional data entry on the line item.
For this entry, the subcontractor received an additional £2,500.00 in new materials that are now stored on the job site (or in a storage facility). The payment application contact enters £2,500.00 in the New Materials Stored column (see 1). After the entry, Procore automatically update these values (see 2).
Total completed & stored to date (%). Procore update this value from 16% to 36%.
Materials presently stored. Procore update this value from £2,000.00 to £4,500.00.
Total completed & stored to date (£). Procore update this value from £2,000.00 to £4,500.00.
Balance to finish. Procore subtracts the sum of the 'New materials stored' value and the 'Previous material stored' amount from the 'Scheduled value' amount. This shows the cumulative decline of the contracted amount.
Note: The Work completed from previous application (%) value remains unchanged (see 3).

Next, half of the new materials stored on the first payment application were installed on the job site during the current valuation period. To address this, the payment application contact takes £1,000.00 from the Previous materials stored column (see 1) and moves that £1,000.00 to the Work completed this period column (see 2).
After you change the entry in the Previous materials stored column, the system the system focus jumps to the Work retention this period (£) column. This occurs if the payment application administrator enables the retention setting on the commitment. To keep to the purpose of billing for stored materials, retention data entry is not included in this example. However, documentation about retention is available:
To learn how to enable retention on a commitment, see Enable retention on a purchase order or subcontract.
To learn how to set and release retention on a payment application, see Set or release retention on a subcontractor payment application.

After moving the Previous materials stored amount to the Work completed this period column, Procore considers the entry to calculate these values:
Total completed & stored to date (%). Procore keeps the value at 36%.
Materials presently stored. Procore keeps the value at £3,500.00.
Total completed & stored to date (£). Procore keeps the value at £4,500.00.
Balance to finish. Procore subtracts the sum of the 'New materials stored' value and the 'Previous material stored' amount from the 'Scheduled value' amount. This shows the cumulative decline of the contracted amount.
Note: The Work completed from previous application (%) value remains unchanged.