Shift Project Dates

Shift Project from the Assignment Gantt

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. Click the expand Icon Expand Materials Esticom icon to expand the project.

  4. Press and hold the SHIFT key and select the project, categories, assignments, and requests to shift the project and maintain the tasks timing and spacing.
    Note: If you only select the project, the project's start and end dates will move but the project's categories, assignments, and requests will retain their original dates.

  5. Click and hold the last selection, then move the grouping to the desired dates using a drag and drop operation.