Permissions
Required Permissions:
Create a project schedule:
Standard level or higher permissions
Add users:
Admin level permissions are needed
View a Schedule
Standard level or higher permissions
Edit a Schedule
Standard level or higher permissions
Limitations:
When retrieving Lookaheads, it is recommended to use a 'rolling wave approach and specify a date range, as an activity can only be retrieved once.
Updates must be manually imported from the native schedule to reflect changes in Procore.
Retrieval of .XER files is currently available, but should be available in a future release.