Permissions

Required Permissions:

  • Create a project schedule:

    • Standard level or higher permissions

  • Add users:

    • Admin level permissions are needed

  • View a Schedule

    • Standard level or higher permissions

  • Edit a Schedule

    • Standard level or higher permissions

Limitations:

  • When retrieving Lookaheads, it is recommended to use a 'rolling wave approach and specify a date range, as an activity can only be retrieved once.

  • Updates must be manually imported from the native schedule to reflect changes in Procore.

  • Retrieval of .XER files is currently available, but should be available in a future release.