Update the bill of quantities

 Important

Before you get started, important things to know about the Bill of Quantities:

  • What is the accounting method? A payment application administrator sets the accounting method for your contract. This cannot be changed. To learn more, see How do I set the accounting method for a contract or funding?

  • For companies using a multi-tier variation configuration setting for contract management in Project Financials:

    • The 'variations' section is only visible and available when the company's Procore administrator has enabled the two (2) or three (3) tier variation configuration on the commitment. See Configure the number of commitment variation tiers.

    • After expanding a line in the 'variation' section, click the commitment variation line(s) and potential variation line(s) in order to expand them until you reach the data entry line item.

Amount-based accounting method

Use this method to invoice lump sum amounts for the payment application line items on the (BOQ). Procore automatically calculates and adjusts the other entries on the line item for you. If you want to release retention, enter a pound amount as needed. Depending on your specific commitment, you may also have the option to bill for stored materials (pictured below). For details about the additional columns that appear when billing for stored materials, see About stored materials on payment applications.

Click here for more detailed information about the amount based accounting method.

The amount-based accounting method requires data entry of lump sum amounts for each line item on the bill of quantities. Note that Procore uses your entries to automatically calculate and update values in other columns.

  1. Review each line item on the bill of quantities:

    • Item number. Shows the line item number.

    • Budget code. Shows the budget code assigned to the line item.

    • Description of work. Shows the description for the line item.

    • Scheduled value. Shows the scheduled value for the line item on the commitment contract. This is the line item's contract value.

    • Work completed from previous application (%). If previous payment applications were created for this commitment, this cell shows a percentage value that represents the work completed during previous valuation periods.

  2. Enter your bill for work completed during the current valuation period:

    • Work completed this period. Enter an amount for the current valuation period.

      Example

      If you completed half of the work for the line item, enter the amount in the Work completed this period column. For example, enter £250.00. Procore automatically calculates and update these columns for the line item:

      • Total completed & stored to date (£). If the line item has a scheduled value of £500.00, Procore adds £250.00, which is 50%. This represents the amount of the total work for the line item on this payment application plus any amount(s) from past valuation periods.

      • Total completed & stored to date (%). If the line item has a scheduled value of £500.00, Procore changes the column value to 50%, which corresponds to your entry of £250.00. This represents the amount of the total work for the line item on this payment application plus any amount(s) from past valuation periods.

  3. If you received materials this valuation period and are storing them on the job site (or in a storage facility), you have this option:

    • Conditional: New materials stored. Enter the amount of any new materials being stored for the current valuation period. Your entry should exclude any cost entered in the 'Work completed this period' column.

       Note

      If the payment application administrator turned ON the 'Enable billing separately for stored materials' setting for the commitment, enter a pound amount for materials for this valuation period. Your entry automatically calculates the values in these columns: 'Total completed & stored to date (£) %' and 'Total completed & stored to date (%).'

    • Previous materials stored. If this is the first payment application, this value is £0.00.

       Note

      If there are previous payment applications, this value shows the cumulative amounts entered in 'New Materials Stored' on those payment applications. A payment application contact cannot modify this setting.

    • Materials presently stored. Shows the amount of the materials being stored during the current valuation period.

    • Total completed & stored to date (£). Shows the amount of the work completed and materials stored on the job site for the current payment application and on payment application(s) for past valuation period(s).

  4. If you are submitting a payment application requesting to release a retention amount:

    • Total retention released. Enter the amount of retention that you are requesting to be released this valuation period.

       Note

      Note that you can request the amount to be released, but you are not permitted to change the retention rate.

    • Total retention. Shows the cumulative amount of retention released for the line item.

  5. Continue the steps above for each line item.

Unit-based accounting method

Use this method when Payment Applications for materials you've ordered in quantity. With this method, you either enter a percentage value 'Total progress' column or a monetary value in the 'Work progress' column. Procore automatically calculates and adjusts the other entries on the line item for you. If you want to release retention, you can enter a pound amount in the 'Retention released' column needed.

Click here for more detailed information about the unit-based accounting method.

The unit-based accounting method requires you to enter a quantity and unit price for each line item on the BOQ. With this method, Procore automatically calculates line item totals for you.

 Note

An asterisk (*) in the list below indicates that you can edit the value of the BOQ line item on your payment application.

  • Quantity
    Shows the total number of units for the line item.

  • Unit price
    Shows the expense incurred for each unit for the line item.

  • Value
    Shows the total pound amount of the line item. This is the sum of the unit price + quantity values.

  • Previous quantity
    Shows the total number of units payment application in previous valuation periods.

  • Previous value
    Shows the total pound amount payment application in previous valuation periods.

  • Total progress %.*
    Enter a percentage amount that reflects your total progress. Your entry must reflect the cumulative progress of any previous valuation periods and the current valuation period.

  • New quantity.*
    Enter a new quantity to reflect the quantity being billed this period on the new payment application.

     Note

    A Icon Calculator calculator icon indicates that Procore automatically calculates the line item's Amount based on the entries in the Qty, UoM and unit cost fields. Click here to see an example.

  • New value.*
    Enter a new value to reflect the value of the line item being billed this period on the new payment application.

     Note

    A Icon Warning Estimating warning icon indicates a user's Amount entry overrides the automatic calculation with a custom amount. Click here to see an example.

  • Retention released.*
    Enter a pound amount of retention to be released this valuation period.

  • Total retention
    Shows the total pound amount of retention to be released for the line item.