Configure settings: Main contracts
Background
When setting up a Procore project, a user with 'admin' permission on the Main Contracts tool will first use the steps below to configure the tool's settings for users of the tool. Because users can create a single main contract or multiple main contracts on a single project (see Create main contracts), the settings listed below are applied globally to all of the main contracts in a project:
Contract configuration. Define the number of main contract variation tiers for the project, gives you the option to grant users with 'Standard' permission on the Main Contracts tool, the privilege to create potential variations and the ability to choose if you want to make the Bill of Quantities (BOQ) editable.
Default distributions. Specify the users to include by default on the main contract tool's email notification distributions.
Funding sources. List any funding source related to the main contract. A funding source can include federal, state and local funds, bonds, grants, tax revenue, loans, programmes and more.
You can also set up customised settings to apply to each main contract that your users create in a single project. To learn more, see Edit the advanced settings on a main contract.
Things to Consider
Required User Permissions:
'Admin' level permission on the project's main contract tool.
Additional Information:
Additional setting for a project's main contract are in the tool's advanced setting tab. See Edit the advanced settings on a main contract.
Prerequisites
Determine the number of variation tiers that you want to apply to your project. To learn more, see What are the different variation tier setting in Project Financials?
Steps
Navigate to the project's Prime Contracts tool.
Click the Configure Settings
icon.Under Contract Configuration, do the following:
Number of Prime Contract Change Order Tiers
Select one option from the drop-down list to define how change orders will be managed on the project:ImportantThis setting cannot be changed after the first variation is created on the project.
1. A one (1) tier change order configuration requires users to create only Prime Contract Change Orders. See Create a Prime Contract Change Order.
2. A two (2) tier change order configuration gives users the ability to create potential change order (see Create a Potential Change Order for a Prime Contract) that can then be grouped into a single Prime Contract Change Order) and sent to a user for approval. This is the default setting for Procore projects.
NotesA three (3) tier variation configuration is also available. To learn more, see What are the different variation tier setting in Project Financials?
If your company or project billing process does NOT require you to group all of the approved variations for the month into a single, combined variation for final signature, Procore recommends configuring the two-tier variation configuration setting on the main contracts tool.