What are multi-tiered locations?

Answer

Locations give you the ability to link different Procore items (for example, RFIs, submittals and more) to specific locations on a job site. This helps project team members to pinpoint the exact location(s) on a job site where a defect was observed, where materials are to be installed or where a project variation occurred.

Locations are generally tiered in a hierarchy to associate parent and sub-locations up to six (6) tiers deep. Each location can also include metadata attributes:

  • Code: A unique identifier that can integrate with Document Management naming standards.

  • GIS coordinates: Geospatial coordinates (points, paths/linestrings or polygons) formatted in GeoJSON for interactive project mapping.

  • Type: Categorisation such as Building, Level, Unit, Room or custom types.

  • Description: Contextual notes or details about the location.

Example

  • Tier 1 - building (e.g., building A)

  • Tier 2 - level/floor (e.g., floor 1)

  • Tier 3 - unit (e.g., Unit 101)

  • Tier 4 - room (e.g., Bedroom A)

Your location hierarchy can be generated from drawings, bulk-imported with metadata using the Procore Imports app or manually created in the Locations tool.
If your location hierarchy is imported or manually created, project admins can allow users to create additional locations in other Procore tools, such as the Site Diary, Snag List or RFIs.
See Allow or disallow users to create locations within a tool.

Which Procore tools support multi-tiered location?

This list details the Procore tools and tasks that include a 'location' drop-down list that interacts with the project location manager in the project's admin tool:

See Also