Change management tools

Next, start learning about Procore's change management tools. There are two options for setting up these tools: (1) Enable the variations and change events tools or, (2) Enable only the variations tool.

Variations with change events

Change events are created for anything on a project that looks like it may create an additional cost. Creating a change event allows you to prepare for the cost of a change before it becomes an actual cost. After creating a change event, you can then create an RFQ (request for quote), which is sent to the appropriate subcontractors for pricing. When RFQs are created and responded to by the assigned subcontractors, variations can then be created based upon the submitted quote.

To learn what else you can do with the change event tool, see change event.

Variations without change events

If your team decides not to enable the change events tool, you can still use the variations tool to account for additional cost. For most Procore customers, this change management workflow starts off by creating a potential variation.

  • Create a potential variation. Use a potential variation to manage any additional cost affecting the main contract. When creating a potential variation, you can only enter a pound amount. Later, when you update the Bill of Quantities (BOQ) for the potential variation, you'll have the option to select a budget code. Ideally, the potential variation will affect a budget code already on the project's Budget. This allows you to see the Budget increase in the project's Budget tool. See Create a potential variation for a main contract.

  • Create a commitment variation. After the potential variation is created, you move on to create a commitment variation. The commitment variation acts as a request for pricing from the subcontractor who will be responsible for completing the scope of work that you outlined in the potential variation. You can compare the commitment variation to the corresponding potential variation and view your variance between the two. To learn more, see Create a commitment variation from a main contract variation.

  • Create a variation request. After you've created potential variations, you can package one or multiple potential variations into variation requests. Variation requests are typically the documents that are submitted for approval and can be used for submitting either individual potential variations or for grouping potential variations in order to streamline the review and approval process. See Create a variation request.

  • Create a main contract variation. Next, you can begin creating variations. Note that when you set a variation's status set to Pending, it appears in the 'Pending budget changes' column of the Budget tool. After the prime contract change order is set to Approved, the total pound amount change is reflected in the 'Approved COs' column of the Budget tool. Approved variations can be added to main contract payment applications. For details, see Create a main contract variation.

  • Create a commitment variation. A commitment variation outlines variations in cost that affect the contract between the general contracting company and a vendor or subcontractor. Once you have marked the commitment variation as approved, the pound change will be reflected in the "committed cost" column on the Budget tool. Commitments and potential commitment variations with a status of "Pending" will show up in the "pending cost changes" column on the Budget tool. See Create a commitment variation.

To learn what else you can do with the Variations tool, see Variations