Ajouter des quantités produites budgétées
Navigate to the project's Budget tool.
Click the Production Quantities tab.
Click Add Line.
Under Budgeted Production Quantities, do the following:
Cost Code. Enter the cost code that corresponds to the budgeted production quantity for that cost code. These entries should exactly match the cost codes in your Procore project. If you enter a cost code that doesn't exist, the import will fail. Cost codes can be added as segment items in Procore's Work Breakdown Structure.
Qty. Enter the budgeted quantity for that cost code using whole numbers.
UOM. Select a Unit of Measure (UOM) from the drop-down list. To learn about the default selections in this list, see Which units of measure are included in Procore's master list? and Add a Unit of Measure to the Unit of Measure Master List.
Note
Vous ne pouvez pas ajouter de postes pour les quantités produites budgétées avec des unités de mesure de la catégorie « Temps » dans l’onglet Quantités produites.
Click Save.