Imports
Note
This page describes recommended best practices for importing submittals to Procore. Click here to view tutorials, videos, and more about the project's Submittals tool.
This page describes recommended best practices for importing submittals to Procore. Click here to view tutorials, videos, and more about the project's Submittals tool.
Submittal Imports is the most efficient method to bulk generate a submittal registry with detailed data for your project’s submittals and packages. This guide will show you the best practices to help you maximize efficiency when using Submittal Imports. Are you ready?
You can add many details to the submittal items at the creation time by utilizing an XLSX or CSV spreadsheet and the Procore Imports application. Duplicating data across multiple items is much more efficient to do within a spreadsheet compared to adding the data individually for each submittal item.
Submittal Imports are done using Procore Imports, which is only available for computers running Windows 10 or higher. See Import Submittals into your Project Level Submittals Tool (Procore Imports). For Mac users, our Customer Support team is available to assist with these imports. See Send a Completed Submittals Import Template to Procore.
Ensure the user or users assigned as Submittal Manager have been added to the project's Directory tool. See Add a User Account to the Project Directory.
If you will be assigning another company as the 'Responsible Contractor' for one or more submittals, ensure that each company has been added to the project's Directory tool. See Add a Company to the Project Directory.
If your project is using locations and you want to add location information to your submittals, the location tiers must already exist in Procore. See Add Tiered Locations to a Project.
If your company is using the project's Specifications tool to manage specs, upload the project specs to Procore (see Upload Specifications) or manually add them to Procore.
If you will be using the Submittal Schedule Calculations feature, be sure to enable it within the project's Submittals configuration settings prior to import. See Enable Submittal Schedule Calculations.
First, download the submittals import template directly from the Procore Imports app or from our Support site here: Download the Submittals Import Template.
Do not delete or move any columns in the template. Doing so will cause the import to fail. You can, however, hide any unused columns.
Submittal Imports can only be used to create new submittals, not to update existing ones.
All date formats must be entered using the date format MM/DD/YYYY, regardless of the project’s settings. Other fields, such as Spec Section Number, can be formatted as needed.
For most fields referencing existing data in Procore, the data entered on the import must match exactly what is in Procore. Otherwise, the import will display an error message or create unwanted new records.
If you prefer to number submittals as you receive them, you can leave the Submittal Number cells blank or add the number 0 to all of them.
Completed import templates do not need to be unique for each project. If you consistently create the same or similar submittal items for each project, you can create a master template to duplicate and edit as needed for each new project. This can act as a template submittal registry and will save you considerable time on future projects.
There are no limits to the number of submittal imports you can perform on a project. It might be useful to separate the imports by priority for large projects.
Submittal Packages (Columns A-D in the template) are not required but highly recommended. See Best Practices: Submittal Packages - Introduction for more information.
Submittal Schedule Calculation fields (Columns R-U in the template) are highly recommended to help you understand whether your submittals are on target. See Best Practices: Submittal Project Configurations for more information.
See Prepare Submittals for Import to the Procore Imports App for additional information.
Procore's Submittal Imports and Submittal Builder are the two most efficient methods to create a Submittal Registry, but they should not be used in tandem. The lists below show advantages and disadvantages for each option to help you determine which is the best choice for your projects.
Le générateur de livrables peut réduire considérablement le temps nécessaire à la génération d’un registre des livrables.
Le générateur de livrables utilise la ROC pour identifier et ajouter le texte du livrable de la section du cahier des charges dans la description du livrable.
Le générateur de livrables crée des livrables avec des détails très limités, de sorte qu’il y aura probablement plus de travail nécessaire pour ajouter les données manquantes (manuellement ou via une modification en masse)
Le générateur de livrables ne peut être exécuté qu’une seule fois par révision de section du cahier des charges
Le générateur de livrables n’est disponible qu’en anglais pour les États-Unis, le Canada et l’Australie.
Il existe des exigences strictes concernant le formatage du cahier des charges afin d’utiliser efficacement le générateur de livrables.
Vous avez besoin d’un registre des livrables simple et rapide sans beaucoup d’informations détaillées.
Les importations sont beaucoup plus détaillées en ce qui concerne la quantité de données qui peuvent être incluses lors de la création initiale.
Les livrables importés nécessitent moins de modifications manuelles ou en masse pour leurs données, par exemple :
Dossiers de livrables
Dates d’étape de l’approvisionnement en matériaux
Lieux
Vous pouvez importer autant de modèles terminés que nécessaire
La création du registre sur le modèle d’importation est manuelle et n’extrait pas automatiquement les données de Procore (telles que les sections du cahier des charges ou d’autres textes)
Les importations nécessitent l’intervention d’un programme tiers pour modifier un fichier XLSX ou CSV, tel qu’Excel ou Google Sheets
Vous décidez d’utiliser des lots de livrables
Vous souhaitez utiliser les champs de calcul du planning des livrables de Procore pour déterminer les dates de « Soumission prévue avant le ».
Vous avez un projet complexe, tel que plusieurs phases, pour lequel vous avez besoin de livrables distincts pour chaque phase
For more information and recommendations about creating a Submittal Registry using Submittal Builder, see Best Practices: Submittal Builder.
Now that your submittal registry has been created from the import, we recommend using Procore's Submittal Packages feature to initiate a workflow for multiple submittal items. See Best Practices: Submittal Packages - Creation and Review.
Alternatively, Procore's bulk actions feature can add a workflow to multiple submittal items from the list view. See Best Practices: Submittal Project Configurations.