Update the Schedule of Values
Important
Before you get started, important things to know about the Schedule of Values:
What is the accounting method? An invoice administrator sets the accounting method for your contract. This cannot be changed. To learn more, see How do I set the accounting method for a contract or funding?
For companies using a multi-tier change order configuration setting for Contract Management in Project Financials:
The 'Change Orders' section is only visible and available when the company's Procore Administrator has enabled the two (2) or three (3) tier change order configuration on the commitment. See Configure the Number of Commitment Change Order Tiers.
After expanding a line in the 'Change Orders' section, click the commitment change order line(s) and potential change order line(s) in order to expand them until you reach the data entry line items.
Amount-Based Accounting Method
Use this method to invoice lump-sum amounts for the invoice line items on the Une ventilation des coûts (VDC) est une liste de postes qui détaille tous les coûts convenus (par exemple, main-d’œuvre, matériaux, etc.) sur un projet. Abrégé en VDC, il détaille le montant du contrat en éléments de paiement individuels pour montrer comment la somme totale du contrat est allouée à l’ensemble du travail du projet. Une ventilation des coûts est également basée sur le budget approuvé du projet et est couramment utilisée pour déterminer les paiements échelonnés au ou aux entrepreneurs.
Previous Materials Stored. If this is the first invoice, this value is $0.00.
Note
If there are previous invoices, this value shows the cumulative amounts entered in 'New Materials Stored' on those invoices. An invoice contact cannot modify this setting.